Construction sites
We are constantly renewing and expanding roads, drinking water pipes and sewers.
We therefore ask for your understanding that this may occasionally lead to disruptions. We have summarized the larger construction measures for you. Please note that the times given are only approximate.
Measure | Section | Resort | Estimated construction time |
---|---|---|---|
Kevelaer Peter-Plümpe-Platz | Annastrasse, Peter-Plümpe-Platz | Wastewater, Water and Road construction | August 2023 to 3. Quarter 2025 |
Twisteden Elisabethstraße | Extension | Wastewater, Water and Road construction | December 2024 to March 2025 |
Kevelaer Nordstraße | Nordstraße 1 | Waste water | November 2024 to December 2024 |