Preliminary building decision and building permit
Description
If new buildings are erected or changes are made to buildings, a building permit is required, unless they do not require a building permit. The building permit is issued in writing if the building project does not conflict with any public law regulations that are examined in the building permit procedure. Before submitting a building application, a preliminary building inquiry can be submitted to the building authorities for a binding preliminary decision. The resulting preliminary decision binds the building authorities for a period of three years. It is possible to query the current status of building applications via the electronic building and approval procedure.
Forms
- Information on structural fire protection for the building application as a supplement to the building description
- Application for deviation, exception and exemption in accordance with Section 69 of the NRW Building Code
- Application for listed building permission
- Application for an excavation permit under monument law
- Application for permission to divide land or issue a negative certificate
- Notification of the removal of installations in accordance with Section 62 (3) of the North Rhine-Westphalia Building Code
- Building application or application for preliminary decision simple building permit procedure
- Building application or application for preliminary approval for advertising structures in accordance with Section 10 of the Building Regulations
- Building application or application for a preliminary decision in accordance with Section 65 of the NRW Building Regulations
- Building description (Annex I/7 to VV BauPrüfVO)
- Construction description for the site drainage system